California

Civil Procedure

Rule 3.2237 – List of responsible parties

Respondent public agency must provide the petitioner or plaintiff, not later than three court days following service of the petition or complaint on the public agency, with a list of responsible agencies and any public agency having jurisdiction over a natural resource affected by the project.

Cal. R. Ct. 3.2237

Rule 3.2237 adopted effective July 1, 2014.