California

Civil Procedure

Rule 3.503 – Requests for extensions of time or to shorten time

(a) Assigned judge may grant request

The assigned judge, on terms that are just, may shorten or extend the time within which any act is permitted or required to be done by a party. Unless othierwise ordered, any motion or application for an extension of time to perform an act required by these rules must be served and submitted in accordance with rule 3.501(17).

(b) Stipulation requires consent of assigned judge

A stipulation for an extension of time for the filing and service of documents required by the rules in this chapter requires approval of the assigned judge.

(c) Extension does not extend time for bringing action to trial

Nothing in this rule extends the time within which a party must bring an action to trial under Code of Civil Procedure section 583.310.

Cal. R. Ct. 3.503

Rule 3.503 amended and renumbered effective January 1, 2007; adopted as rule 1503 effective January 1, 1974; previously amended effective January 1, 2005.