A party cannot object that no demand for the subject matter of a civil action was made prior to its institution unless it is expressly set up by way of defense in the answer or reply and is also accompanied with a tender of the amount or thing that is due; in which case, if the plaintiff will further prosecute the civil action and shall not recover a greater sum or more than is tendered, the plaintiff shall pay all costs. This provision is applicable as well to actions for property as for money; when property is tendered the damages for its detention, if any, shall also be tendered.

Mo. R. Civ. P. 55.31

Adopted Jan. 19, 1973, eff. Sept. 1, 1973. Amended Sept. 28, 1993, eff. Jan. 1, 1994.